Main Switch Board installed at ECR
Floor plate installed
Cables from Main switch board to engine room equipments are pulled
Cables from MCC to engine room equipments are pulled
Generator Exhaust line, Fuel line, Coolinglines are complete
Generators Gravity tank relacate above the generator
Structural fabrication for Echo sounder is in progress