Only 22 of the 1,517 housing projects approved under Jawaharlal Nehru National Urban Renewal Mission were completed by the due date of March 2011, the Comptroller and Auditor General has stated, while noting that the ministries of central government were "not equipped" to monitor a project of this magnitude.